Offshore Pipelines: Hydrostatic testing of the submarine pipeline system commences only after complete installation works of pipelines, risers,
crossings, free-span corrections,
trenching/ burial/ backfilling operations, and remedial works, if any. Sectionalization of offshore pipelines is impractical for
hydrotesting, and the complete pipeline is tested in one shot. However, sometimes the connected piping such as the riser, topside piping (the section between the riser top and scraper trap), spools, flexibles, hoses, and laterals are excluded from the
strength test of the offshore pipeline (but included in the
system leak test), depending upon contractual obligation, installation sequence and ease of execution in subsea. Before
hydrostatic testing of the pipelines, in-line ball valves located on the lateral connections and PLEMs are kept in the partially open or crack-open position, and the check valve flapper is locked in the open position. During the
hydrostatic testing, in-line valves shall not be closed for making pipeline sections, and
hydrostatic testing shall not be performed against the closed valves, particularly if the valve is soft seated.
Hydrostatic tests shall be conducted in accordance with approved
Hydrostatic Test Diagrams (HTD), clearly indicating the number of test sections along with minimum and maximum
test pressures in each test section. Any flexible pipe or hoses for permanent installation shall not be included in the pipeline
hydrostatic strength testing and shall be tested separately as per their manufacturer's guidelines.
Onshore/ cross-country pipelines: The pre-commissioning
hydrostatic test for the onshore pipeline commences only after the completion of mechanical and civil works, i.e., after acceptance of all
welds and backfilling of the entire pipeline section. The
hydrostatic test also includes those sections which have been previously tested (pretested), viz., pipeline sections installed at
Rail/ road crossings, major water crossings by
HDD (horizontal directional drilling) etc. A pre-determined/ calculated pipeline section length shall be selected for the hydrostatic test based on ground elevation,
water availability, and location of sectionalizing valve stations and/ or terminals. The availability of
test water along the pipeline route sometimes dictates the length and arrangement of test sections.
Graph showing the ground elevation of the complete test section shall be plotted to verify that the
test pressures at the high and low points are within the specified limits before the start of the test. In addition, it helps divide the total pipeline length into various hydrotest sections, wherein the difference between the highest and lowest ground elevation within the hydrotest section is minimum. The pressure difference between the highest and lowest point within the
hydrotest section is equal to the change in pressure gravity head ( ∆
Pg ) which is calculated as below:
∆ Pg = ∆ h ∙ ρ ∙ g
Where,
∆Pg |
= |
Change in pressure due to gravity head |
∆h |
= |
Difference in height between the highest and lowest point |
ρ |
= |
Density of test fluid (generally water) |
g |
= |
Acceleration due to gravity |
The value of
change in pressure due to gravity head ( ∆
Pg ) may appear small compared to the required
hydrotest pressure. However, it plays a vital role in sectionalizing the pipeline for hydrotest, mainly when the minimum
hydrotest pressure is close to the pipe's minimum yield strength (SMYS) e.g., 90% of SMYS. After meeting the requirement of minimum pressure at the highest point of the section equal to 90% of SMYS, only 10% of SMYS of the pipeline material can compensate for the difference in pressure due to gravity head and fluctuation in pressure due to temperature change. Hence, as a rule of thumb, the maximum length of the test section for onshore/ cross-country pipelines is kept within 50 km for
thermal stabilization, control gravity head, ease of
filling and pressure monitoring during the hydrotest.
Note: If the above-ground or above-water section length exceeds 3 % of the total test section length, then it may result in temperature fluctuation as the exposed section will receive additional heat transfer due to sun’s radiation. Hence, a separate hydrostatic pressure tests for the above-ground/ above-water and the buried/ submerged sections shall be carried out to minimize the influence of temperature fluctuation during the test.
Hydrotest Test Procedure: Before
hydrotesting, a hydrostatic test procedure which includes the detailed procedure for the
cleaning,
gauging,
filling,
hydrotesting &
dewatering of pipeline strings, is prepared and submitted to the Company. A statement of responsibility for the test supervisor and his/ her team is also included in the hydrotest procedure. The test procedure includes, in general, but not be limited to:
- List of nominated personnel to supervise the pressure testing operations with their qualifications, tasks, responsibilities, and authorities.
- Detailed schedule giving proposed dates of the main activities, tests, and mobilisation dates of the nominated personnel.
- Details of the selected test sections, including assemblies and pre-test sections.
- Identification of potential safety and environmental hazards, including the necessary measures and emergency plans.
- Details of the line-fill water, including the source, treatment method, discharge/disposal and permits.
- Details of the test equipment, including layouts and size and/or performance. A valid calibration certificate for the instruments proposed to be used shall also be included.
- Details of the test section preparation, including cleaning, gauging, and filling.
- Details of the hydrostatic pressure test preparation, including temperature stabilisation period.
- Details of the hydrostatic pressure tests, including pre-test, strength test, leak-tightness test and pipeline system test.
- Details of the post-testing activities, including depressurising and documentation.
- Details of rectification activities, including the proposal for locating leaks, dewatering and leak rectification.
Hydrotest Test Equipment/ Instrumentation: Any test equipment pressurized during the test operations shall be designed for a working pressure not less than the
test pressure. These components shall have material certificates, and the equipment shall have data sheets from the Manufacturer. The test equipment connected to the test section shall have hydrostatic test certificates and shall have been tested to a pressure of at least 1.25 times the
test pressure of the test section. The test equipment shall be internally clean and fit for purpose.
The Equipment / Instruments to be used for performing the work shall include, but not limited to the following:
- Pigs for filling, cleaning, and gauging:
- Cleaning pigs
- Four cup batching pigs
- Gauging pig with gauge plate diameter equal to 95% of thickest wall pipe in the pipe sections.
- Water Filling Pumps:
- Water filling pump with differential head 20% greater than the maximum required and flow rate preferably between 400 m3/h and 1000 m3/h.
- Positive displacement pump equipped with a stroke counter and capable of exceeding the maximum test pressure by at least 20 bar.
- Positive displacement meters to measure the volume of water used for filling the line having a valid calibration certificate.
- Portable tank of sufficient size to provide continuous supply of water to the pump during pressurization.
- Armoured type flexible hose can be used in short lengths, for pressurising the test section.
- Pressure gauges of suitable pressure range and accuracy with valid calibration certificate.
- Pressure recorder to continuously record the pressure.
Test Medium: Cleaning,
filling, and
hydrotesting is performed using soft non-aggressive water, free from sand and silt, and withdrawn from a suitable source along the pipeline route. Only clean, fresh water from a river, aquifer or potable water system or clean seawater from the open sea should be used. Brackish water from estuaries or harbours are avoided as a source wherever possible.
The water used for pressure testing is selected from a source with a temperature close to the pipeline's ambient temperature. This minimizes the
thermal stabilization period required to bring the temperature of the
line-fill water equal to the ambient temperature. The water is filtered through 50-μm (2 mils) filters, except for water injection lines, which are filtered through 2-μm (0.08 mils) filters before entering the test section. The arrangement of filters at the test work sites should enable back-flushing without disconnecting the pipe work.
The water is tested in an approved lab for its non-aggressiveness and suitability as the test medium. Depending on the quality of water, the duration of contact of line-fill water with the interior of the test section, the pre-commissioning requirements and the future use of the pipeline, treatment packages containing an oxygen scavenger and biocide is added to the line-fill water. The environmental acceptability of any proposed treatment package, e.g. toxicology, Biochemical Oxygen Demand (BOD), Chemical Oxygen Demand (COD) etc., shall be demonstrated after filtering/ separation and/or neutralization. Environmentally acceptable line-fill treatment packages should be used.
To minimize biological fouling and/ or bacterial corrosion to an acceptable level in the filled pipeline, the above concentrations should not exceed the following limits:
- sulphate concentration 42 mg/kg (42 ppm)
- fatty acids concentration 14 mg/kg (14 ppm)
- ammonium concentration 3 mg/kg (3 ppm)
If water from aquifers is used, the analysis should show all components and their concentrations. Where the line-fill water is to be transferred from one test section to another, the quality of the water should be checked, and the water should be chemically retreated as necessary before it is moved into the test section. In addition, the water should be refiltered through 50-μm (2 mils) filters to reduce the entrainment of debris from one test section to another.
Line filling should not occur if the ambient temperature is below 2°C (36°F) unless a suitable antifreeze has been added to the line-fill water. If a
hydrostatic pressure test is to be carried out in freezing conditions, the Contractor shall provide the required data for the pressure/ temperature variation calculation before performing the test. The
test equipment required, and the disposal of the antifreeze/water mixture should be included as part of the
test procedure.